ALDOT’s November 16 traffic plan for Hammondville I-59 includes closing the southbound entrance and exit ramps at Exit 231 and routing those trips by US-11. The November 13 announcement scheduled the shift for Monday, November 16; the records checked for this guide do not establish whether the change has been implemented.
In the announced arrangement, southbound through traffic uses the northbound roadway while a five-mile section is reconstructed. Concrete barriers separate the opposing directions. That through route and the ramp detour serve different trips.
The Alabama Department of Transportation’s November 13 notice described Wiregrass Construction’s planned diversion while crews demolish and replace the aging southbound roadway. ALDOT described the segment closure as lasting about a year. The notice gave no exact reopening date.
For local trips, the interchange restriction matters separately from the interstate diversion. Exit 231 serves SR-40/SR-117; both its southbound entrance and exit ramps are included in the closure. ALDOT identifies US-11 as the detour.
What changes at Hammondville I-59
| Trip or project element | November 13 plan | What to distinguish |
|---|---|---|
| Southbound through traffic | Northbound inside lane, scheduled from November 16 | Planned diversion, not closure of the entire interstate |
| Exit 231 southbound access | Entrance and exit ramp closures with a US-11 detour | Ramp access differs from through travel; implementation is unverified here |
| Work area | Extends north past milepost 235 and south past milepost 230 | This is the roughly five-mile phase |
| Full reconstruction contract | Covers about 16 miles from the Georgia line toward Fort Payne | Its completion schedule is longer than this phase |
For Hammondville I-59, the ramp restriction and the through-traffic diversion answer different travel questions. Interchange users need the ramp information even when traffic continues past the exit. The full contract boundary matters separately to readers tracking construction progress and cost.

Northbound drivers on Hammondville I-59 should also check the work-zone notice because the plan puts traffic in both directions on their roadway during this phase.
These are announced arrangements, not a live road-condition report. Check ALGO Traffic before departure for the current restrictions and any change to the planned shift. No additional turn-by-turn route or travel-time estimate is supplied in the notice.
Why a northbound reopening precedes a southbound diversion
The Hammondville I-59 records trace separate northbound and southbound contracts. The September reopening and the November diversion concern different sides of the interstate, rather than the same roadway reopening and then closing for one job.
Its September 25 northbound update reported the opening of a reconstructed four-mile section between Hammondville and Sulphur Springs. That marked substantial completion of an eight-mile, $41 million northbound project. The update also explained that crews would reposition barriers for a later southbound diversion.
The May southbound project announcement had already described later phases using extended southbound closures and two-way traffic on the northbound roadway. The November notice identifies the next specific section and planned shift date.
Read together, those records explain why a recently rebuilt roadway will carry both directions while the other side is replaced. They do not establish that every nearby I-59 construction restriction has ended.
Hammondville I-59 phase versus the full project
The current southbound project page lists project IM-I059(427), a cost of $47,544,196 and projected completion in winter or spring 2029. Its scope is reconstruction and rehabilitation along about 16 miles.
The earlier May announcement estimated February 2029. The current project page uses the broader seasonal window. Neither should be read as the reopening date for the five-mile Hammondville phase, which the November notice describes separately as about a year.
For a separate Etowah County project, see the SR-77 bridge replacement between Southside and Rainbow City. That report explains the anticipated early 2027 construction start and the plan to carry both directions on the existing southbound bridge during much of the work. That later bridge arrangement is separate from the November 16 Hammondville interstate shift.
Before using the Hammondville I-59 southbound ramps at Exit 231, check ALGO Traffic’s current map for the restrictions affecting that trip. The announced November 16 date does not by itself establish that the diversion or ramp closures are active. If the current agency information differs from this plan, use the current information.